Aluminum Roller Shutter Door installation steps (Need 3 installers):

(1) Open the aluminum alloy rolling door box and check the list of accessories and main parts;
(2) Finding the site, finding the installation center line on the door hole, and determining the lateral installation reference of the bracket plate, the rolling door and the side rails;
(3) Based on the lower edge of the door frame, determine the upper and lower mounting standards of the bracket plate, the spool shaft, the roller assembly, the rolling door and the side rails;
(4) Install the bracket plate to the corresponding position above the door frame. After the bracket plate is installed in place, ensure that there is a gap of about 2 mm between the two ends of the roller blind door and the flange for adjustment;

(5) Place the reel shaft of the aluminum alloy rolling door on the flange of the bracket plate. The two ends of the reel shaft are fastened with a split pin. One person holds the reel, and the other two adjust the guide rails and sealing strips on both sides of the rolling door. To the installation position (longitudinal beams on both sides of the door);

roller shutter 13

(6) Install the lower jaw to the specified position. When installing, first clean the lower edge of the door frame, remove the double-sided adhesive protection paper on the lower jaw, and install it in place;
(7) Roll the rolling door from the upper end of the roller on both sides and slide it into the guide through the upper end of the two side rails, and then fix the two side rails and sealing strip on the longitudinal beams on both sides of the door (on-site with tapping and tapping fixing) ), after the installation is completed, it should be ensured that the rolling door can be pulled up smoothly;
(8) Pull the roller blind down to the lock position, and insert the positioning pin and the flange at one end of the spindle (with two holes), and insert the positioning pin at the other end (see Figure 1), and turn the curtain tube toward the door. Slightly rotate so that the upper locating pin can be taken out (note: you can't release your hand at this time, so as not to cause the roller blind to swivel and rub the hand);
Aluminum alloy rolling door roller installation diagram
When installing the rolling door, the up and down stroke of the rolling door may be adjusted to ensure that the opening and closing of the rolling door is light, safe, accurate and reliable.
(9) Debugging method: Hold the handle with both hands and try to pull up and down the rolling door to adjust the strength of the torsion spring. Open the door (slightly assisted upwards) and add too much.
The method of adding and subtracting the spring force: first insert the upper positioning pin, loosen the screw on the connecting strip of the curtain tube, separate the connecting belt from the curtain tube, and then add the force to the direction of closing the door, and the direction of opening the door is Force reduction

(10) After installation, clean up the site.

roller shutter


Related Products List

Home

Product

Whatsapp

About Us

Inquiry

We will contact you immediately

Fill in more information so that we can get in touch with you faster

Privacy statement: Your privacy is very important to Us. Our company promises not to disclose your personal information to any external company with out your explicit permission.

Send